companies

Subsidiaries

Zarand Iranian Steel Company (Private Equity) as a new uprising and dynamic company in steel industry was registered in company registration bureau under the ID number 333265 with a capital account of ten billion Rials on 19.11.2008.See more >

Coke Dry Quenching “CDQ”
  • Geolocation of the project location : Kerman . Zarand Km 7 is the road of zarand
Project progress ( Finished )
Zarand Iron Ore Concentrate Development Plant
  • Geolocation of the project location : Kerman province, Zarand city, adjacent to Jalalabad Iron Ore mine
  • Input Capacity : 4.6 million tons per year
  • Output capacity : 2 million tons per year
  • Employment rate : 250
Project progress ( Finished )
Pabdana coal processing plant
  • Geolocation of the project location : Kerman province, Zarand city, 2 km from Kianshahr town and 28 km from Kohbanan city, Ghaemshahr city
  • Input Capacity : 934 thousand tons of crude coal per year
  • Output capacity : 472.5 thousand tons of coal concentrate per year
  • Employment rate : 80
Project progress ( Finished )

Introducing and operating iron and steel making plant and the related units, in order to develop and expedite mines and mining industries in Iran.See more >

Production of bardsir steel
  • Geolocation of the project location : Kerman Province, km 45 Kerman-Bardsir Road, 6 km road
  • Input Capacity : 1 million tons of sponge iron and 117 thousand tons of iron scrap per year
  • Output capacity : 1 million tons steel billets per year
  • Employment rate : 600
Project progress ( Finished )
Sponge iron production of Bardsir
  • Geolocation of the project location : Kerman Province, km 45 Kerman-Bardsir Road, 6 km road
  • Input Capacity : 1.5 million tons per year
  • Output capacity : 1 million tons per year
  • Employment rate : 200
Project progress ( Finished )
Sirjan iron ore pellet production plant
  • Geolocation of the project location : Kerman Province, Sirjan County, adjacent to Gol Gohar Iron ore
  • Input Capacity : 2.5 million tons per year
  • Output capacity : 2.5 million tons per year
  • Employment rate : 300
Project progress ( Finished )

Butia Steel Company is pursuing to build future through collaboration and Organizational Citizenship Behavior (OCB). Our ultimate goal is serving our customers, employees, shareholders, suppliers and local communities and respecting environmental and social values.See more >

Combined power plant of Botia
  • Geolocation of the project location : 17 km of Imam Reza (AS) belt, near Kazemabad village, Chrud district, Kerman province
  • Output capacity : 500 megawatts of electricity
  • Employment rate : 150
Project progress ( 89.6 Percent )
Butia Steel Making Plant
  • Geolocation of the project location : Kerman, km 17 Belt of Imam Reza (AS), near Kazemabad village, Chrud district
  • Input Capacity : 1.6 million tons of sponge iron and 165 thousand tons of iron scrap per year
  • Output capacity : 1.5 million tons of steel billets and steel billets per year
  • Employment rate : 2000
Project progress ( 96.2 Percent )
Butia iron ore pellet production plant
  • Geolocation of the project location : Kerman, km 17 Belt of Imam Reza (AS), near Kazemabad village, Chrud district
  • Input Capacity : 2.5 million tons of iron ore concentrate per year
  • Output capacity : 2.5 million tons of iron ore pellets per year
  • Employment rate : 300
Project progress ( Finished )

Iranian Babak Copper Company (IBCCO) was recently founded and registered in Tehran with the reference No. of 379679. IBCCO’s asset is 10,000,000,000 Iranian Rials. It is a subsidiary of the Middle East Mineral Industries and Mines Development Holding Company (MIDHCO). See more >

Production of copper pipes
  • Geolocation of the project location : Kerman province, Kerman city, Shahrbabak industrial town
  • Input Capacity : 12 thousand tons of copper cathodes per year
  • Output capacity : 12 thousand tons of copper pipes per year
  • Employment rate : 100
Project progress ( Finished )
Copper Cathode Production Plant
  • Geolocation of the project location : Kerman province, 20 km north of Babak city
  • Input Capacity : 250 thousand tons of copper concentrate per year
  • Output capacity : 50 thousand tons of copper cathodes per year
  • Employment rate : 300
Project progress ( Finished )

Middle East Standard Industry Engineering Co. was registered in Tehran, on 09/01/2010 under the ID NO. 363098 and with the capital of 5 billion Rials as a subsidiary of MIDHCO.See more >

Copper Cathode Production Plant
  • Geolocation of the project location : Kerman province, 20 km north of Babak city
  • Input Capacity : 250 thousand tons of copper concentrate per year
  • Output capacity : 50 thousand tons of copper cathodes per year
  • Employment rate : 300
Project progress ( Finished )
Tabas Coal Preparation Plant
  • Geolocation of the project location : South Khorasan province, 100 km south-east of Tabas city, Parvah coal mine, opposite East Pars
  • Input Capacity : 1000 thousand tons of crude coal per year
  • Output capacity : 505 thousand tons of coal concentrate per year
  • Employment rate : 80
Project progress ( Finished )
Lime and Dolomite production and baking plant
  • Geolocation of the project location : Kerman province, 30 km northwest of Kerman city, the site of the Iranian Bhutan Steel Company
  • Input Capacity : 304 thousand tons of limestone and 152 thousand tons of dolomite annually
  • Output capacity : 264 thousand tons of lime and 132 thousand tons of dolomite annually264 thousand tons of lime and 132 thousand tons of dolomite annually
  • Employment rate : 150
Project progress ( Finished )

To buy and sell and invest in mines and minerals industry inside and outside of the company, commercial and economic operations, including the procurement and supply of trading and trading services, import and export of all mineral items, equipment, machinery from inside and outside and abroad, the production of various types of minerals and mineral products, specialized consultancy in mines and related products and investments inside and abroad, obtaining the representation of mineral products and related industries inside and abroad, the establishment of representing in other places inside and outside of the country in relation to the activities related to the other real, legal and productive characters and with Regan both business and what may have authorized transactions the above areas inside and outside of the country will be possible.See more >

Chah Mousa copper production plant
  • Geolocation of the project location : South Khorasan province, 100 km south-east of Tabas city, Parvah coal mine, opposite East Pars
  • Output capacity : 500 tons of copper cathode
  • Employment rate : 89
Project progress ( Finished )
Tabas Coal Preparation Plant
  • Geolocation of the project location : South Khorasan province, 100 km south-east of Tabas city, Parvah coal mine, opposite East Pars
  • Input Capacity : 1000 thousand tons of crude coal per year
  • Output capacity : 505 thousand tons of coal concentrate per year
  • Employment rate : 80
Project progress ( Finished )

Ferrosilice Gharbe Pars Co. (special joint stock company) has been registered in the registration office of Hamedan province on 11/2/89 under the ID No. 9150 with a capital of 23 billion Rials.See more >

Producing the development of Furosilcium
  • Geolocation of the project location : Hamedan Province, Malayer City, Jokar City, Jokar Industrial Town
  • Input Capacity : 24 thousand tons of quartz per year
  • Output capacity : 12 thousand tons of Ferrosilicon a year
  • Employment rate : 100
Project progress ( Finished )
production of Furosilcium
  • Geolocation of the project location : 50 km of Hamadan Road - Malayer, Glass Industrial Estate
  • Input Capacity : 24 thousand tons of quartz per year
  • Output capacity : 12 thousand tons Ferosilisses per year
  • Employment rate : 130
Project progress ( Finished )

This firm has been established in 2006. Since Kerman is unique in its geology and mining resources and also the need for having a coal processing firm in Pabdana, the coal concentrate firm with the capacity of 550000 tons per year has been established in 2010, based on the knowledge and expertise of a management team and updated technology. See more >

Pabdana coal processing plant
  • Geolocation of the project location : Kerman province, Zarand city, 2 km from Kianshahr town and 28 km from Kohbanan city, Ghaemshahr city
  • Input Capacity : 934 thousand tons of crude coal per year
  • Output capacity : 472.5 thousand tons of coal concentrate per year
  • Employment rate : 80
Project progress ( Finished )

Middle East Shining Sun Commercial Co (MESSCO) has been activated on 20/12/2008 with the asset of 10 billion Rials, as a subsidiary company of (MIDHCO).See more >

IDR Construction Company (MANA) was established in 1974 with the objective of execution of large industrial buildings, warehouses, multistory offices and residential buildings. Since its establishment, IDR Construction Company has executed several major projects thus playing its role in progressing towards achieving the country’s objectives regarding development and industrialization. Some of these projects include: steel rolling mill plants, machine manufacturing factories, agro- industrial complexes, sugar factories, power stations, breakwater, office and residential complexes and main oil reservoirs.See more >

IMICO has been registered on Oct. 11, 2020 with the registration number 566710 and the national number 14009503410 in the Companies Registration Office.See more >